Completion of 2026 JCC High School Renovations
August 06, 2026
The start of school for JCC will be on schedule as renovations to the high school are wrapping up. The HVAC systems have been installed and are undergoing final checks. The fire sprinkler systems have been installed along with the fire alarm system. Ceiling tiles have been replaced and cleaning of the building is underway.
However, when school starts on Monday, August 10, students and staff will not have access to the lower level of the high school. This includes the locker rooms, band room, art room, JAG classroom, weight room, Spanish classroom and shop areas. Mr. Damme and Mrs. Reuter have worked hard to make accommodations for these classes to take place in other parts of the building or the elementary building. The lower level is planned to be completed by Tuesday, August 18 with all classrooms and programming back to their original spaces.